Which of the following refers to use of the ‘management by exception’ technique?

A.
Providing a Dashboard Report with a transparent chain from strategic intent to benefits
realization
B.
Specifying points at which reviews of initiatives are linked to funding release
C.
Reporting via the documented route and schedule
D.
Referring variances from plan that exceed control limits to the portfolio governance body