Which of the following is obtained from the Identify step of the Risk Management Process?

Which of the following is obtained from the Identify step of the Risk Management Process?

A.
The downstream effect of the risk

B.
The priority of the risk

C.
The probability of the risk

D.
The mitigation of the risk