Which is the main reason that an MoV Project Plan needs to be reviewed when the Business
Case changes?

A.
To maintain business profitability
B.
To ensure that the choice of team members is still appropriate
C.
To ensure selected tools and techniques are still appropriate
D.
To ensure that the Value Profile reflects the changed needs of the business
Explanation: