Which is recorded in the risk register in the ‘identify – risks’ step? seenagape 10 years ago Which is recorded in the risk register in the ‘identify – risks’ step? A. Lessons learned from completed activities B. Responses to risks C. Assessed probability of risks D. Description of the risk ← Previous question Next question →