Which is NOT a reason why it becomes more difficult to implement changes identified by a MoV Study a

Which is NOT a reason why it becomes more difficult to implement changes identified by a MoV
Study as a project progresses?

A.
Sunk costs increase as a project progresses

B.
Project team members gain increased ownership of their work

C.
Resistance to change increases

D.
Project objectives are less clear

Explanation: