Which is NOT a reason why it becomes more difficult to implement changes identified by a
MoV Study as a project progresses?

A.
Sunk costs increase as a project progresses
B.
Project team members gain increased ownership of their work
C.
Resistance to change increases
D.
Project objectives are less clear