Which is MOST APPROPRIATE when estimating costs where the scope is uncertain?

A.
Wait until the scope is certain and then estimate
B.
Estimate only those areas where the scope is certain
C.
Start with an initial best guess estimate and update it as more information becomes known
D.
Develop a cost model and refine the scope to meet the cost model
Explanation: