Which is an underlying success factor for a P3O model with an Organization Portfolio Office?

Which is an underlying success factor for a P3O model with an Organization Portfolio
Office?

A.
Funding model for a P3O approved

B.
Challenge to current PPM culture or processes provided

C.
Highly skilled senior, experienced staff utilized

D.
PPM maturity of level 3 or above achieved