Which is an activity of the Deliver process within the permanent P3O lifecycle?

Which is an activity of the Deliver process within the permanent P3O lifecycle?

A.
Monitor the rate of change in the PPM community

B.
Conduct formal post-implementation reviews

C.
Design the implementation plan to deliver early critical improvements

D.
Define the future state of P3O provision