Which is a true statement about acceptance criteria?

Which is a true statement about acceptance criteria?

A.
Acceptance criteria are used to produce the customer’s quality expectations
Configuration Item Records

B.
Acceptance criteria are less specific and precise than customer’s quality expectations
Business Case

C.
Once agreed, acceptance criteria CANNOT be changed
Project Brief

D.
Acceptance criteria should be agreed between the customer and the supplier
project management team and/or role descriptions

A.
Acceptance criteria are used to produce the customer’s quality expectations
Configuration Item Records

B.
Acceptance criteria are less specific and precise than customer’s quality expectations
Business Case

C.
Once agreed, acceptance criteria CANNOT be changed
Project Brief

D.
Acceptance criteria should be agreed between the customer and the supplier
project management team and/or role descriptions

Explanation:
QUESTIONNO:180
Identify the missing words in the following sentence.
When planning the next stage, the Project Manager needs to review and, if necessary, update the
[ ? ] with regard to external resources or suppliers.