Which is a common barrier to implementing the risk management process?

A.
Lack of a high-risk appetite at senior management level
B.
Lack of an appropriate response to a risk in an activity’s risk register
C.
Lack of an assigned risk owner
D.
Lack of risk facilitation resources and time