Which information from the risk register is used during the ‘assess – evaluate’ st

Which information from the risk register is used during the ‘assess – evaluate’ step to
calculate the total risk exposure of an activity?

A.
Identified risks resulting from a risk response action

B.
Estimated likelihood of the risks occurring

C.
Exposure of the risks after completion of risk responses

D.
The timeframe in which the risks are likely to occur