Which information from the risk register is used during the ‘assess – evaluate’ step to calc

Which information from the risk register is used during the ‘assess – evaluate’ step to calculate the
total risk exposure of an activity?

PrepAway - Latest Free Exam Questions & Answers

A.
Identified risks resulting from a risk response action

B.
Estimated likelihood of the risks occurring

C.
Exposure of the risks after completion of risk responses

D.
The timeframe in which the risks are likely to occur

Explanation: