which document would contain details of that change? seenagape 10 years ago If the Project Board instructs the Project Manager to implement a request for change, whichdocument would contain details of that change? A. Checkpoint Report B. Highlight Report C. Issue Report D. Product Status Account ← Previous question Next question →