Which BEST describes the ‘reduce the threat’ risk response option?

Which BEST describes the ‘reduce the threat’ risk response option?

A.
Changing the planned tasks in an activity

B.
Performing an action to minimise the chance of a risk impacting objectives

C.
Monitoring a risk to ensure it remains within acceptable tolerance

D.
Partaking in a pain/gain contract with another party for a specified risk

Explanation: