Which BEST describes the ‘reduce the threat’ risk response option?

A.
Changing the planned tasks in an activity
B.
Performing an action to minimise the chance of a risk impacting objectives
C.
Monitoring a risk to ensure it remains within acceptable tolerance
D.
Partaking in a pain/gain contract with another party for a specified risk