When is the milestone review report signed off in the Project Planning SMF?

When is the milestone review report signed off in the Project Planning SMF?

A.
After approving the request for change

B.
After approving the functional specification, master project plan and master schedule

C.
After it has been transferred to IT Operations

D.
Before approving the functional specification, master project plan and master schedule