When can the building and testing of a Change begin?

A.
As soon as the impact analysis has been discussed by the members of the Change Advisory Board
B.
As soon as there is a correct network plan for the change
C.
As soon as the Request for Change (RFC) has been formally authorized
D.
As soon as the Request for Change (RFC) has been classified
I choose C