What product records any time tolerances agreed between the Project Manager and Team Manager? seenagape 10 years ago What product records any time tolerances agreed between the Project Manager and TeamManager? A. Product Description B. Work Package C. Project Initiation Documentation D. Stage Plan ← Previous question Next question →