What process is used by the Project Manager to maintain focus on delivery of a stage’s product

What process is used by the Project Manager to maintain focus on delivery of a stage’s products
within agreed tolerances?

A.
Directing a Project

B.
Controlling a Stage

C.
Managing a Stage Boundary

D.
Managing Product Delivery