What process is used by the Project Board to respond to an Exception Report? seenagape 10 years ago What process is used by the Project Board to respond to an Exception Report? A. Controlling a Stage B. Managing a Stage Boundary C. Managing Product Delivery D. Directing a Project ← Previous question Next question →