What is the expected outcome of the first Sprint on a project?
A.
A few working, tested features from the Product Backlog
B.
Architecture and high-level design of the Product
C.
Assignment of the team, Product Owner and Scrum Master
D.
A well-defined release plan for the Product
Explanation: