Which statement is true regarding this scenario?
A team estimates a Story using the Planning Poker technique. The team decides to allocate five
Story points to the Story, because the Developers estimated two points and the Testers estimated
three points.
Which statement is true regarding this scenario?
Why does the Daily Scrum need to be held at the same location and time?
Why does the Daily Scrum need to be held at the same location and time?
What is a Scrum-of-Scrums?
What is a Scrum-of-Scrums?
Why is planning poker an effective estimation technique?
Why is planning poker an effective estimation technique?
What term can be used to describe the traffic light?
A team decided to install a large traffic light in the team hall to indicate whether the latest build was
healthy (green), failing a few tests (orange) or failing high priority tests (red).
What term can be used to describe the traffic light?
Which is a statement of value as described in the Agile manifesto?
Which is a statement of value as described in the Agile manifesto?
What value (in days) should be used for planning?
During a Sprint Planning session, the team argues about the work estimates for a particular story.
The Product Owner estimates five days.
The Lead Architect estimates two days.
The Scrum Master estimates eight days.
The team member working on it estimates seven days.
What value (in days) should be used for planning?
which sport is the term "Scrum" and much of the terminology derived?
From which sport is the term “Scrum” and much of the terminology derived?
What should the Scrum Master advise the team to give their main focus, while working in a global distributed t
What should the Scrum Master advise the team to give their main focus, while working in a global
distributed team?
What must a team do to finish the Product Backlog Item it selects?
A team selects a Product Backlog Item (PBI) for the Sprint Backlog.
What must a team do to finish the Product Backlog Item it selects?