In which process is decided whether the change is going to be included in or excluded from this rele

At the last moment, just before the deployment of a new release, it is reported that one of the changes in the release isn’t going to be ready in time. In which process is decided whether the change is going to be included in or excluded from this release?

A.
Planning and resource management

B.
Transition

C.
Change management