If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report? seenagape 10 years ago If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report? A. Corporate management B. Project Board C. Project Assurance D. Project Manager ← Previous question Next question →