If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated seenagape 9 years ago If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to fora decision? A. Senior User B. Executive C. Corporate/programme management D. Senior Supplier ← Previous question Next question →