How is the risk progress report used in the ‘implement’ step?

How is the risk progress report used in the ‘implement’ step?

PrepAway - Latest Free Exam Questions & Answers

A.
Identify the status against the activity’s stated measures for risk management

B.
Identify the scales used to measure the probability and impact of a risk

C.
Describe actions to enhance how risk management is performed

D.
Gain agreement for the amount of risk that can be taken