Which is NOT a valid reason for using entry and exit criteria?

###BeginCaseStudy###
Scenario: 9
Test Management Documentation
A software house is concerned about the number of defects found in software released to its
customers. They are starting to plan a new software product. In the past, releases have
often been stopped due to poor planning and too many defects found during high level
testing. You have been recruited to the newly created position of test manager and asked to
develop a test strategy, manage the testing of the project and organize the resources
needed to carry out the testing.
###EndCaseStudy###

As part of the test strategy, entry and exit criteria will be defined for each test level. Which is
NOT a valid reason for using entry and exit criteria?

Which THREE of the above mentioned characteristics relate to the master test plan?

###BeginCaseStudy###
Scenario: 9
Test Management Documentation
A software house is concerned about the number of defects found in software released to its
customers. They are starting to plan a new software product. In the past, releases have
often been stopped due to poor planning and too many defects found during high level
testing. You have been recruited to the newly created position of test manager and asked to
develop a test strategy, manage the testing of the project and organize the resources
needed to carry out the testing.
###EndCaseStudy###

Within the projects, a master test plan and phase test plan will be used. Following is a list of
characteristics applicable for test plans:
a. Any deviation from the procedures described in the test strategy document
b. The overall estimated costs, timescales and resource requirements
c. A detailed schedule of testing activities
d. The development deliverables to be tested
e. Which test staff members (names) will be involved and when
f. Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan?

Which TWO of the above mentioned characteristics relate to the phase test plan?

###BeginCaseStudy###
Scenario: 9
Test Management Documentation
A software house is concerned about the number of defects found in software released to its
customers. They are starting to plan a new software product. In the past, releases have
often been stopped due to poor planning and too many defects found during high level
testing. You have been recruited to the newly created position of test manager and asked to
develop a test strategy, manage the testing of the project and organize the resources
needed to carry out the testing.
###EndCaseStudy###

Within the projects, a master test plan and phase test plan will be used. Following is a list of
characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan?

Which of the following product risks would be most effectively addressed just by static testing?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

Which of the following product risks would be most effectively addressed just by static testing?

Which of the following checkpoints would be appropriate?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

The development manager is managing the review of the responses received from bidders,
and has asked the in-house test manager to provide a review checklist for the test
management aspects of the responses. Which of the following checkpoints would be
appropriate?

Which one of the following estimation approaches is appropriate at this stage of the project?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

Which one of the following estimation approaches is appropriate at this stage of the project?

Why might a RAD approach be a better option for the test manager rather than a sequential development?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

Why might a RAD approach be a better option for the test manager rather than a sequential
development?

Which of the following is NOT a typical key challenge for testing in a RAD based development approach?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

Which of the following is NOT a typical key challenge for testing in a RAD based
development approach?

Which test technique might be most appropriate to use?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

As a result of the RAD based development approach, the test manager has decided to
change the risk mitigation approach. Which test technique might be most appropriate to
use?

Which of the following would be appropriate as a measure of test coverage?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

The business has asked for a weekly progress report. Which of the following would be
appropriate as a measure of test coverage?


Page 6 of 7« First...34567