Which of the following checkpoints would be appropriate?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

The development manager is managing the review of the responses received from bidders,
and has asked the in-house test manager to provide a review checklist for the test
management aspects of the responses. Which of the following checkpoints would be
appropriate?

Which one of the following estimation approaches is appropriate at this stage of the project?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

Which one of the following estimation approaches is appropriate at this stage of the project?

Why might a RAD approach be a better option for the test manager rather than a sequential development?

###BeginCaseStudy###
Scenario: 10
V3
Online Application
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development (RAO)
approach.
###EndCaseStudy###

Why might a RAD approach be a better option for the test manager rather than a sequential
development?