PrepAway - Latest Free Exam Questions & Answers

Author: seenagape

Which test management control option is most appropriate to adopt under these circumstances?

###BeginCaseStudy###
Scenario: 4
V2
Test Management Tool
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to
increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second
Increment slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver
the application with support for manual testing and then to provide a delivery * weeks later to
resolve any remaining points and provide support for automated testing (i.e. the link to the
capture-replay tool).
– Concerns have been expressed by a section of the user community, that in some places
the usability is very poor.
###EndCaseStudy###

Which test management control option is most appropriate to adopt under these
circumstances?

which one of the following factors is most likely to lead to a revised view of product risk?

###BeginCaseStudy###
Scenario: 4
V2
Test Management Tool
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to
increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second
Increment slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver
the application with support for manual testing and then to provide a delivery * weeks later to
resolve any remaining points and provide support for automated testing (i.e. the link to the
capture-replay tool).
– Concerns have been expressed by a section of the user community, that in some places
the usability is very poor.
###EndCaseStudy###

Risks should be constantly reviewed. Given the current situation, which one of the following
factors is most likely to lead to a revised view of product risk?

Which of the following is least likely to be used as a technique to identify project and product risks?

###BeginCaseStudy###
Scenario: 4
V2
Test Management Tool
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to
increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second
Increment slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver
the application with support for manual testing and then to provide a delivery * weeks later to
resolve any remaining points and provide support for automated testing (i.e. the link to the
capture-replay tool).
– Concerns have been expressed by a section of the user community, that in some places
the usability is very poor.
###EndCaseStudy###

Which of the following is least likely to be used as a technique to identify project and product risks?

Which of the following is a project risk mitigation step you might take as test manager?

###BeginCaseStudy###
Scenario: 4
V2
Test Management Tool
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to
increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second
Increment slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver
the application with support for manual testing and then to provide a delivery * weeks later to
resolve any remaining points and provide support for automated testing (i.e. the link to the
capture-replay tool).
– Concerns have been expressed by a section of the user community, that in some places
the usability is very poor.
###EndCaseStudy###

Which of the following is a project risk mitigation step you might take as test manager?


Page 578 of 897« First...102030...576577578579580...590600610...Last »