Which of the following actions are recommended when implementing a P3O model with Hub Portfolio Offices?

Which of the following actions are recommended when implementing a P3O model with Hub
Portfolio Offices?
1. Appoint a P3O Sponsor to act as Senior Responsible Owner
2. Allow temporary offices to define their own standards and processes
3. Run the implementation as a programme with appropriate governance
4. Use appropriate programme management lifecycles and processes