A data center has experienced a disaster. The current state of SRDF is failed over. The storage administrator
wants to begin transfer of the invalid tracks from the R2s to the R1s while production work continues on the
R2s.
Which SRDF operation should be used?

A.
Update
B.
Failover
C.
Failback
D.
Restore