An SRDF/Star customer wants to move their production from the current workload site to one of
the target sites. Which operational step is necessary before executing the symstar halt command?

A.
Ensure that all host I/O is stopped
B.
Ensure that both targets are in the disconnected state
C.
Ensure that both targets are in the isolated state
D.
Execute a symstar switch command