An EMC customer has a need to backup several remote client machines to a central Co-Location
data center. They have purchased an EMC Avamar to backup their desktop/laptop (DTLT) client
data. The DTLT clients backing up to the Avamar will span three time zones and management of
the Avamar server will take place from the same time zone as the remote data center.
If the customer has a need to start DTLT backups at 10 A.M. daily in their local time zone, which
changes should be made in the Avamar environment to ensure a healthy Avamar system?
A.
Maintenance schedule should be shifted by 12 hours
B.
Time zone of the storage nodes should be changed from UTC
C.
Set Avamar time zone to match the DTLT machines
D.
Schedule the backups to occur at the end of the blackout window