In a particular process, the Review Invoice activity has a different calendar than the one selected
on the process.
Which calendar will the system use to resolve timers created for the Review Invoice activity?

A.
the default system calendar
B.
the calendar applied to the activity
C.
the calendar applied to the process
D.
the calendar with the earliest date