An EMC Avamar customer has an IBM DB2 server with multiple instances; i.e., A, B, and C.
• Instance A = 150 GB
• Instance B = 300 GB
• Instance C = 75 GB
The customer has installed the Avamar DB2 client plug-in on this host and has configured an
online backup schedule for each instance. Which additional step is required prior to starting the
schedules for each instance?

PrepAway - Latest Free Exam Questions & Answers

A.
Migrate Instances B and C to two new DB2 servers

B.
Run db2 update db cfg for <DATABASE-NAME> using LOGRETAIN ON for each instance

C.
Create a file system backup schedule to include the archive logs for each instance

D.
Modify the schedules for each instance to ensure they do not run simultaneously