EMC Exam Questions

What would you verify during planning and design for this project?

ABC.com with a SAN-attached CX3-40 needs to add 10 test servers to the environment. They
want to use iSCSI to attach the servers. They also want to boot the hosts over iSCSI from the
CX3-40.
Assume there is available disk space and iSCSI connectivity into the SAN. What would you verify
during planning and design for this project?

A.
Ethernet switch model, host BIOS revisions, and availability of TOE cards

B.
Network card model numbers, host BIOS revisions, and operating system patch levels

C.
Availability of a dedicated gigabit network, availability of TOE cards, and host models

D.
Compatible operating systems, availability of a dedicated gigabit network, andiSCSI HBA
availability