The task of performing a data migration of resources from three SUN Servers physically connected to a Symmetrix 5 to a newly purchased DMX 1000 has been assigned to you. On arrival onsite you learn that there is a fourth server that needs to be migrated.
What would be the first step you take?

A.
Escalate to Project Management
B.
Reconfigure the Symmetrix to support increased number of LUNs
C.
Recalculate the completion time
D.
Confirm the DMX has available capacity