A customer has an Oracle 11g database running on a RAC cluster with ASM. It occupies
approximately 5 TB on a Symmetrix DMX. They have an RTO of four hours. They intend to
implement PowerSnap with EMC NetWorker version 7.6 to back up the BCVs using RMAN
scripts and a proxy host. What prevents this implementation from being successful?

A.
RTO of four hours cannot be accomplished.
B.
ASM does not support proxy hosts.
C.
BCVs cannot be mounted to a proxy host with a RAC cluster.
D.
PowerSnap is not supported on Oracle 11g with EMC NetWorker 7.6.