In EMC NetWorker, what happens when the high watermark is reached on an AFTD being
managed by the stage resource?

A.
Automatically move save sets to another media
B.
Continuously stage save sets until all the save sets are moved
C.
Automatically clone save sets to another media
D.
Automatically send warning messages to the Administrator
A only works when staging has been setup prior to this happening. Otherwise I assume D.
Since D should happen in any case it is the technically correct answer.
0
0
But the correct answer according to the officially available Pre-Test is A. So they assume that staging has been setup without mentioning it…