A customer plans to locate their primary production site and their secondary disaster recovery site 1,000 kilometers apart. The EMC account team has recommended they use DMX3s running SRDF/A.
During the planning phase, it is estimated that:
The SRDF/A minimum cycle time parameter will be set to 20 seconds It will take 3 hours after a primary site failure to declare a disaster and failover to the secondary site After a failover to the disaster site, it will take two hours to bring up the applications and make the secondary site operational What is the minimum recovery point objective that this supports?
A.
3 hours
B.
5 hours
C.
20 seconds
D.
40 seconds