What is the Recover Point Objective (RPO) of this plan?

During DR planning in a two data center setup you determine that:
The remote site B will hold a copy of data that is 5 minutes behind the production data at site A It will take two
hours after an outage at site A to decide to shift production to site B An additional 3 hours will be needed to
power up the servers, bring up the network and redirect users so site B can become productive
What is the Recover Point Objective (RPO) of this plan?