Starting at the bottom, what is the recommended order for racking components in an EMC Avamar Data Store rack?

Starting at the bottom, what is the recommended order for racking components in an EMC Avamar Data Store rack?

PrepAway - Latest Free Exam Questions & Answers

A.
Switch, utility, storage, spare

B.
Storage, switch, utility, spare

C.
Spare, storage, switch, utility

D.
Switch, utility, spare, storage

One Comment on “Starting at the bottom, what is the recommended order for racking components in an EMC Avamar Data Store rack?

  1. abdullah says:

    there is no any correct answer the correct about that “from bottom to top it is as follows: Utility Node, Spare Node, Storage Node, Switches” as per the material