PrepAway - Latest Free Exam Questions & Answers

Category: E20-555 (v.1)

Exam E20-555: Isilon Solutions and Design Specialist Exam for Technology Architects (update January 28th, 2014)

What is the correct method to continue production operations?

An Isilon customer has two 5-node clusters; one for production and one for disaster recovery (DR).
The customer’s workflows are replicated to the DR cluster through SyncIQ on individual
schedules. They shutdown their production cluster for a scheduled DR test, failed over to the DR
cluster, and continue their DR testing.
Assume both clusters have identical shares, exports, and user authentication and that the client
applications have been stopped and the DNS re-pointed. What is the correct method to continue
production operations?


Page 17 of 23« First...10...1516171819...Last »