Exam E20-553: Isilon Infrastructure Specialist Exam for Technology Architects

What is the best way to stop the failover operation and continue using the primary cluster?

An Isilon customer has a replication policy setup between a primary cluster and a secondary cluster. After the
initial synchronization of the clusters, the primary cluster starts to exhibit issues so the customer initiates a
failover operation between the two clusters. Duringthe failover, the primary cluster becomes fully operational
again. The customer would like to stop the failoveroperation between the two clusters. What is the best way to
stop the failover operation and continue using the primary cluster?

What isthe most likely reason the target cluster did not automatically allow writes of the data into the Smart

An Isilon customer created a scheduled SyncIQ policy to replicate data from an Enterprise-mode SmartLock
directory. The source cluster becomes unusable. Thetarget cluster does not automatically allow writesto the
data in the replicated SmartLock directory. What isthe most likely reason the target cluster did not
automatically allow writes of the data into the SmartLock directory?

What is the correct method to continue production operations?

An Isilon customer has two 5-node clusters; one forproduction and one for disaster recovery (DR). The
customer’s workflows are replicated to the DR cluster through SyncIQ on individual schedules. They shutdown
their production cluster for a scheduled DR test, failed over to the DR cluster, and continue their DRtesting.
Assume both clusters have identical shares, exports, and user authentication and that the client applications
have been stopped and the DNS re-pointed. What is the correct method to continue production operations?

What is the easiest method to continue operations on production?

An Isilon customer has two 5-node clusters, one forproduction and one for disaster recovery (DR). The
customer’s workflows are replicated to the DR cluster through SyncIQ on individual schedules. They have
shutdown their production cluster for scheduled maintenance, failed over to the DR cluster, and are currently
operating from the DR site. Assume both clusters have identical shares, exports, user authentication, and that
the client applications have been stopped and the DNS re- pointed. What is the easiest method to continue
operations on production?