Which is the most likely next step in their transformation process?

A software manufacturer is planning to convert their VDC to IaaS. As part of the transformation to
IaaS the company realizes they have to make several organizational changes. They have already
obtained executive sponsorship and made all the necessary organizational changes.
Which is the most likely next step in their transformation process?

What is the minimum number of nodes that you should configure in the hypervisor cluster?

You are planning to deploy a virtualized application in a high-availability configuration with
automated VM restart on a hypervisor cluster. Your sizing estimates show that peak workload
conditions will saturate the processing power of three hypervisor servers.
To meet the SLA, N+2 redundancy is required on the hypervisor servers, with server utilization not
to exceed 75% under any conditions.
What is the minimum number of nodes that you should configure in the hypervisor cluster?