which of the following prototyping, a version of the system is built to check the requirements and i

In which of the following prototyping, a version of the system is built to check the requirements and
is then discarded?

A.
Evolutionary prototyping

B.
Incremental prototyping

C.
Project prototyping

D.
Throw-away prototyping

Explanation: