which of the following would the project manager use to assess the strengths and weaknesses of the p

After final acceptance, which of the following would the project manager use to assess the
strengths and weaknesses of the project?

A.
Post-project review

B.
Transition plan

C.
Project kick-off meeting

D.
Quality analysis

Explanation: