Which of the following would be used to determine the budget needed to complete the project? seenagape 10 years ago The project has an AC of $5,000. Which of the following would be used to determine the budgetneeded to complete the project? A.ETC B.PV C.BAC D.EAC Explanation: ← Previous question Next question →