A server’s runtime during power outages is too short to shut down properly. A system technician is asked to
remediate the problem. Which of the following would be the result of adding additional batteries to the UPS?

A.
Increased load balancing
B.
Extended uptime
C.
Greater efficiency
D.
Increased power output